The share of hydel energy would be added in two phases.
Islamabad: The Water and Power Development Authority (WAPDA) has devised a comprehensive hydropower generation expansion plan to increase hydel energy share from existing 9406MW to 20,591MW by 2028-29.
As per official sources, the share of hydel energy would be added in two phases.
Under 1st phase, the share of hydel energy would be enhanced from 9406MW to 12,366MW by 2025 and in next phase it would be jacked up to 20,591MW till 2028-29.
The WAPDA officials said, at present, hydel share in overall energy mix stood at 31 per cent with annual energy generation of 37 billion units.
The WAPDA, under its generation plan would add 17 billion units of low-cost hydel electricity raising the number of units from 37 to 54 billion by the year 2025.
Eight terrorists killed in security forces KP operations
- 3 hours ago
Bushra Bibi granted interim bail till Feb 7 in 13 cases
- 2 hours ago
Cold, air pollution: Skin diseases on high in Karachi
- 4 hours ago
Scrutiny fee abolished for first-year exams in Karachi
- 2 hours ago
PTI intra-party elections case set for hearing
- 32 minutes ago
Severe cold wave in country, mercury drops to -11
- 6 hours ago
Ban on mercury use in gold mining
- 3 hours ago
Day marks 13th death anniversary of Arfa Karim
- 6 hours ago
Quetta mine accident; All bodies recovered as operation completes
- 27 minutes ago
71,849 fake, ineligible CNICs in 5 years blocked
- 4 hours ago
JI to protest on Mall Road Lahore on Jan 17
- 3 hours ago
Military trial case: People entering Corps Commander House is security failure: SC
- 3 hours ago