Tarbela: The power generation of the Tarbela dam Monday exceeded its installed capability of 4,888 and produced 4,993 megawatts (MW) of electricity.
According to the Tarbela dam spokesperson, 105 MW of extra electricity was produced by the 17 power generations units of the dam where the installed capacity was only 4,888.
Owing to the huge increase in water inflow in the Tarbaila Dam reservoir which was 314,500 cusec feet and outflow was 234,500 cusecs feet which increased the water level of the dams to 1,524 feet.
During the last two weeks, water storage level and power production of the dam also increased while during last week after reaching the dangerous level the auxiliary spillways were opened to discharge extra water into river Indus.
All 17 power generation units were working with full capacity and were producing 4,993 megawatts of electricity.
The maximum water storage capacity of the Tarbela dam is 1550 feet at present water level has reached 1524 feet, it is expected that in the coming few days the dam would reach its maximum storage capacity as it has crossed its installed capacity of production.
Tarbela Dam is an earth-filled dam along the Indus River in Khyber Pakhtunkhwa province. It is the largest earth-filled dam in the world.
The dam is 143 metres (470 ft) high above the riverbed and its reservoir, Tarbela Lake, has a surface area of approximately 250 square kilometres (97 sq mi).
Death anniversary of Lollywood legend Sultan Rahi observed
- 5 hours ago
Brea, Kentucky hand Florida first loss of season
- 2 hours ago
Are North Carolina Republicans trying to steal a state Supreme Court seat?
- an hour ago
Why Barcelona can't play Dani Olmo or Pau Victor ... for now
- 2 hours ago
The madman theory of Trump and tariffs
- an hour ago
Explosive Los Angeles wildfires rage on even as fierce winds ebb
- 5 hours ago
Lebanese parliament elects army chief Joseph Aoun new president
- 10 hours ago
Yet to get 40 Tejas ordered in 2010: IAF chief
- 11 hours ago
'Year of Reforms': What Indian Army has planned in 2025
- 10 hours ago
Govt saved Rs1.1tr through talks with IPPs: Awais Leghari
- 5 hours ago
Pakistan announces squad for Physical Disability Cricket Champions Trophy 2025
- 5 hours ago
Shah Mehmood, others indicted in May 9 arson case
- 16 hours ago