PM orders early completion of inquiry report regarding Neelum-Jhelum project closure
Prime Minister Shehbaz Sharif directs to immediately complete the investigation report regarding the recent closure of the Neelum-Jhelum Hydropower Project


Islamabad: Prime Minister Shehbaz Sharif on Sunday instructed to take stern action against those responsible for defects arising in the Neelum-Jhelum Hydropower Project.
Chairing a meeting regarding the Neelum-Jhelum Hydropower Project in Islamabad, he directed to immediately complete the investigation report regarding the recent closure of the Neelum-Jhelum Hydropower Project.
The Prime Minister further said it is unfortunate that concrete lining was not done, despite defects in the design pointed out by experts. He said what an irony it is that criminal negligence was committed in such a big and important project.
He questioned as to why a detailed geological survey was not conducted regarding the project. He further said that criminal negligence was committed by not doing third-party validation of the project.
Shehbaz Sharif advised to immediately form a committee for the reactivation of the Neelum-Jhelum Hydropower Project.
Former Interior Secretary Shahid Khan and head of the investigation committee probing the recent malfunctions in the Neelum-Jhelum Hydropower Project presented the preliminary investigation report in the meeting.
The meeting was briefed that reduction in power generation occurred on 29th April this year due to pressure drop in the right and left headrace tunnels of the Neelum-Jhelum Hydropower Project. Similarly, power generation was completely stopped on second May this year.
It was told that the closure of the project is causing a loss of millions of rupees to the national exchequer. It was said the place where the current fault occurred is the rock burst zone.
The meeting was further apprised that a significant decrease in power generation was noticed during the PTI regime in 2021 due to abnormal drop in pressure in the headrace tunnel, but this matter was ignored and not reported and deliberately put under the carpet.
It was informed that during the PTI regime, no repair work was done regarding the fault in the Neelum-Jhelum Hydropower Project in 2021, which continued to multiply the losses. It was a criminal negligence.
The meeting was told that the fault occurred in 2021 in the Neelum-Jhelum Hydropower Project is also being made part of the investigation report. It was further briefed that the power generation remained suspended in 2022 due to fault in tailrace tunnel of the project.
The meeting was apprised that geophysical and seismic factors were ignored in the construction of the Neelum-Jhelum Hydropower Project and adequate concrete lining of headrace tunnel was not done. It was said that the third-party validation of project not done well in time.
Huge crowds gather in Iran as funeral ceremonies for assassinated supreme leader begin
- 2 days ago

5 books that define America — for better and for worse
- 2 days ago
Argentina survive Cape Verde scare to reach World Cup last 16
- 2 days ago

Gold prices resume declining trend in Pakistan, global markets
- 2 days ago

Amazon has enough satellites to launch its Starlink competitor
- 8 hours ago

The evidence against “ultra-processed” foods is weaker than you think
- 21 hours ago

The Supreme Court can no longer explain itself
- 2 days ago

PSDF, FPCCI partner to strengthen industry-led skills development and employment pathways
- 14 hours ago

America’s housing was built for a world we no longer live in
- 2 days ago

The solution to America’s 250th birthday mess? Party like it’s 1976.
- a day ago
Swift and Kelce marry as global stars swarm 'royal wedding'
- 2 days ago

How will citizens get their passports now? Here's you know
- 2 days ago




.jpeg&w=3840&q=75)