Augmentation work of existing 160 MVA, 220/132 kV autotransformer (T-8) with 250 MVA, 220/132 kV autotransformer has been completed by Project Delivery (North) Lahore
Lahore: National Transmission and Despatch Company Limited (NTDC) on Monday successfully added a 250 MVA autotransformer at 500 kV Grid Station Sheikhupura to enhance its power transmission capacity.
The augmentation work of existing 160 MVA, 220/132 kV autotransformer (T-8) with 250 MVA, 220/132 kV autotransformer has been completed by Project Delivery (North) Lahore, the autotransformer successfully energized on Monday.
A shutdown was approved up to 14-08-2024 for this work, however, NTDC team completed the project 03-days before the scheduled shutdown period by deploying extra resources.
The augmentation of this autotransformer will enhance the loading capacity of 500 kV Grid Station Sheikhupura and provide relief to the areas under Lahore Electric Supply Company (LESCO). The enhanced capacity of this grid station will ensure smooth power supply, which will benefit the domestic, commercial and industrial consumers.
Deputy Managing Director (AD&M), Engr. Rasheed A. Bhutto and Deputy Managing Director (P&E), Engr. Qaiser Khan appreciated the Project Delivery (North) Lahore team for successful completion of the project.
-
Business 4 hours ago
Gold price shoots up Rs1,300 per tola in Pakistan
-
Pakistan 2 days ago
Attack on Qazi: British police visit Pakistan High Commission
-
Pakistan 2 days ago
Smog issue is old, can’t be solved overnight: CM Punjab
-
Sports 1 day ago
Pakistan lose fifth quick wicket in T20I chase against Australia
-
Technology 4 hours ago
New ‘Draft’ feature in WhatsApp
-
Pakistan 22 hours ago
Bilawal blames PML-N of not fulfilling political agreements
-
Business 2 days ago
Petroleum product likely to be expensive for second consecutive time
-
Regional 13 hours ago
The new (and familiar) faces staffing the second Trump administration