Augmentation work of existing 160 MVA, 220/132 kV autotransformer (T-8) with 250 MVA, 220/132 kV autotransformer has been completed by Project Delivery (North) Lahore
Lahore: National Transmission and Despatch Company Limited (NTDC) on Monday successfully added a 250 MVA autotransformer at 500 kV Grid Station Sheikhupura to enhance its power transmission capacity.
The augmentation work of existing 160 MVA, 220/132 kV autotransformer (T-8) with 250 MVA, 220/132 kV autotransformer has been completed by Project Delivery (North) Lahore, the autotransformer successfully energized on Monday.
A shutdown was approved up to 14-08-2024 for this work, however, NTDC team completed the project 03-days before the scheduled shutdown period by deploying extra resources.
The augmentation of this autotransformer will enhance the loading capacity of 500 kV Grid Station Sheikhupura and provide relief to the areas under Lahore Electric Supply Company (LESCO). The enhanced capacity of this grid station will ensure smooth power supply, which will benefit the domestic, commercial and industrial consumers.
Deputy Managing Director (AD&M), Engr. Rasheed A. Bhutto and Deputy Managing Director (P&E), Engr. Qaiser Khan appreciated the Project Delivery (North) Lahore team for successful completion of the project.
-
Sports 1 hour ago
Arshad Nadeem declines offers from other countries to play for them
-
World 2 days ago
Bangladesh CJ to resign following students protest
-
Sports 1 day ago
Javelin superstar Arshad Nadeem receives hero's welcome at Lahore airport
-
Pakistan 1 day ago
Stability not possible in Pakistan with stolen elections: Khaqan Abbasi
-
Pakistan 2 days ago
Arshad Nadeem to receive grand welcome at Lahore airport tonight
-
World 2 days ago
Tokyo rocked by magnitude 6.8 earthquake
-
Pakistan 2 days ago
Justice Abid Aziz swears-in as Acting CJ of LHC
-
Business 1 day ago
Gold prices expected to rise in Pakistan