CPEC-funded 660kV Matiari-Lahore transmission line begins commercial operation from today
Lahore: The 660 kV HVDC Matiari-Lahore Transmission Line, a flagship project under CPEC, has begun its commercial operation from today successfully as per agreed timeline between the National Transmission and Despatch Company Ltd (NTDC) and Pak Matiari-Lahore Transmission Line Company (PMLTC).


Prior to its COD, as many as eight power tests on different voltage levels were performed successfully. The power test include Commissioning Tests (DC Station Tests) Lahore (A1:), Commissioning Tests (DC Station Tests) Matiari (A2:), Mono-pole Low Power System Tests (Upto 400 MW each pole) (A:3),Bi-pole Low Power System Tests (Upto 800 MW Bi-pole) (A4:), Mono-pole High Power Tests (2200 MW, each pole) (A5:),Bi-pole High Power Tests at Maximum Available Power (MAP) (A6:), Special Optional Tests (recommended by OE)( A7:).
Whereas, the last test i.e Trial Operation (168 hrs) and Capability Demonstration Test (06 hrs) (A8:) has been successfully completed on 18.08.2021, says a press release issued by the NTDC.
In this regard, a ceremony was held at WAPDA House Lahore, attended by Managing Director NTDC Engr Azaz Ahmad and Ms Zhang Lei, the President and CEO of PMLTC and other reps from both companies were also present on the occasion.

NTDC chief Engr Azaz Ahmad appreciated Chinese company for completion of the project in time, saying first ±660 kV HVDC Matiari Lahore Transmission Line would bring stability in NTDC transmission network after having being crossed many bridges successfully.
The 878 kilometers 4,000MW project has been completed by Pak-Matiari Lahore Transmission Company (Pvt) Limited, on Built-Own-Operate-Transfer (BOOT) basis for a term of 25 years. The project will evacuate power from the new generating units located in the south including Thar coal-based projects.
The ECC on July 25, 2017 approved the Security Package Documents i.e. Implementation Agreement (lA) and Transmission Services Agreement (TSA) which were subsequently executed on May 14, 2018. The NTDC will be responsible for operation and maintenance of the transmission line.
HVDC technology is a maiden addition in the national grid of the country, though it’s been widely used for a long time around the world, and the need of long-distance high-power transmission from generating stations in the far-flung areas towards densely located load centers.
The said project is a milestone for NTDC when it comes to diversifying the national grid and it will serve a great deal towards NTDC mission of a reliable, efficient and stable national grid.
Pentagon says Iran will not be ‘endless war’
- 6 hours ago

President, PM express grief over Ayatollah Khamenei’s martyrdom
- a day ago

Trump’s war with Iran, briefly explained
- 18 hours ago

Pakistan's Cyber Force launches retaliatory attack on India with slogans of Pakistan Zindabad
- 8 hours ago
Pakistan won’t allow use of neighboring territory to destabilize peace: President
- 4 hours ago

High-level meeting reviews country’s security situation
- a day ago

Operation Ghazab Lil-Haq: Pak Army responding effectively to Afghan Taliban's aggression
- a day ago

Pakistan Army destroys ammunition depot of Fitna-al-Khwarij, Afghan Taliban in Khost
- 9 hours ago
Hockey World Cup Qualifier: Pakistan beat Malaysia to reach semi-finals
- 4 hours ago

Bloodbath at PSX as KSE-100 plummets over record 16,000 points
- 7 hours ago
How Finland defeated fascism
- 18 hours ago
Several US warplanes crashed, crew survived: Kuwait defence ministry
- 10 hours ago